i really needed the push

July 19-20

Well one Saturday,  my brother-in-law shows up with some teenager help to tackle the cement board. I was a little surprised, I generally like to work at my own pace (glacier slow) but it worked out so great, I'm super happy. Not much to it, just measure, measure again and then cut (score and snap). Screw the piece in and start on the next. It took us about 4 hours to complete, with a pause for lunch.

i'm impressed with myself, this looks all pro-like


added a package with etch-a-sketch and note in the ledge cavity

Everything was wonderful, and the next day I had delusions of mudding and taping but something was bothering me. The pipe from the shower faucet doesn't look right. I dug around for the instruction guide (that the plumber had used to install it) and its totally off. Holy @#*& now I have to call the plumber back.